News of Jinhui Mining in 2016
addtime:2020-06-23 view:

 1. On the morning of August 17, Deputy Secretary of the Provincial Committee, Governor Linduo and his party visited Jinhui Mining to investigate the project construction.

Governor Lin pointed out during the survey: green mountains surround here and famous trees reflect, every single project is a well-crafted beautiful garden. The enterprise pays attention to technological innovation, mine safety and human warmth, and is really a good modern enterprise. You adhere to the road of technological innovation and environmental protection, which has played a leading role in the development of traditional mines. Jinhui Mining has high-degree automatic controls, perfect safety production systems and humane measures in place, you must continue to play advantages, quicken pace, become bigger and stronger to seek welfare for employees, create value for the society and set a new benchmark.

 

 

 

2. The Central Environmental Protection Insp. 7 visits Jinhui Mining to supervise the environmental protection work.

On December 19, Vice Team Leader of the Central Environmental Protection Insp. 7, vice-minister of the Environmental Protection Huang Runqiu and his party visited Jinhui Mining to supervise the environmental protection work, the inspection team affirmed the Jinhui Mining’s overall work: Jinhui Mining consciously fulfill the responsibility of environmental protection, focus on concept guidance to build a green mine, harmonious development and standardization of the environmental supervision, pay attention to environmental management and increase environmental investment, planting trees and grass to beautify the environment has achieved great effects.

 

 

3. The completion ceremony of the 1.5 million tons/year lead-zinc mining project of Jinhui Mining is grandly held.

Gou jiagou lead-zinc mine was listed as the first major project in the province to accelerate the resources exploration, development and transformation by the provincial government. The major projects, such as mining, dressing, tailings, safety, environmental protection, ecotourism, water- power supply and logistics had been completed by three years’ hard work. On September 20, 2016, the “1.5 million tons/year lead-zinc mining project of Jinhui Mining” ceremony was held, which marked Jinhui Mining had entered the trial production and was an important milestone in the development history of Jinhui Mining.

 

 

4_2.jpg

 

4. The top forum of “well-known business schools, cultural Jinhui trip” and “making green classics, inheriting cultural Jinhui” is held in Jinhui Mining.

From August 27 to 28, more than 100 representatives from the seven national famous business schools including Peking University Business School, Fudan University Business School, Cheung Kong Graduate School of Business, CityU. Business School of Hong Kong, Business School of Shanghai Jiaotong University and World Chinese Musicians Association gathered at Jinhui Mining and carried out the top forum of “well-known business schools, cultural Jinhui trip” and “making green classics, inheriting cultural Jinhui”. The elites gave high affirmation and praise to the advanced construction concept, modern green mine and eco-park.

 

13.jpg

 

5_.jpg

 

5. The mining project of Gou jiagou lead-zinc mine successfully realizes the test run with material

On the morning of April 20, with issuing the startup command, the mining and dressing equipment slowly started, and the automatic control system realized the successful linkage, which marked Jinhui Mining had entered a new stage of on-line debug from the project construction.

 

 

 

6. The Party Committee of Jinhui Mining is awarded “Pioneer of building a well-off society”

In 2016,the Party Committee of Jinhui Mining was awarded the “Pioneer of building a well-off society” by the provincial non-public Party Working Committee, which was the first provincial honor obtained by Jinhui Mining.

 

 

 

7. The underground roadway is precise and cross-linked

The return airway of Jinhui Mining’s 6# to 3# wells was precisely opened at 17:00 April2, the successful completed project not only improved the ventilation condition of the later underground construction, but also lay a solid foundation for accelerating the mining step. At the same time, the key project of 2# and 3 # wells 650 middle section rail transport roadway, connecting the south and north ore belts, was successfully connected as planned, which had strategic significance to the formation of the whole underground mining system.


8.jpg


8. The power supply network of Jinhui 110KV substation is all formed

On the afternoon of February 29, Jinhui Mining completed the load switch of tailings pond, 4# well and water pumping station, which marked the power supply network of Jinhui 110KV substation was all formed.


變電站1.jpg

 

    ?